November 2004
The workshop that
was of special interest recently was a Work Breakdown Structure
session held with a team of 15 people for a little more than half a
day. We started at 11.00am, served a working lunch and finished at 5:00
p.m.
Once again, a wide range
of people from the Systems organisation and the User community needed
to agree on a plan of action and the sequence of events necessary to
complete a major project that encompasses three distinct User groups.
The Project Manager needed
the team to complete three levels of conversation:
- First, everyone had to agree on the Key Deliverables for the project.
- Then, for each Key Deliverable a set of Work Packages were defined.
- Finally, for each Work Package, the specific Tasks required to complete
them were noted. The task definition was recorded on sticky pads and
displayed on “wallpaper” so that everyone in the room could
see the whole picture, literally!
Once all the tasks had been
identified in breakout sessions, the team reviewed the entire effort,
identified dependencies, noted priorities and estimated timeframes for
completion.
The Project Manager
agreed to take all of the output from the session and transpose the
“wallpaper” into a formal document. To give you an idea
of the scope, there were about 60 Work Packages identified. The team
left both pleased with what had been accomplished and concerned about
the workload that lies ahead.